Dig the holes on the ground for the post at every 2m, or 2.5m, or 3m, or 5m , the common hole size is 300mm-500mm . depth is 500mm-1000mm. alignment keep them in the line. Every 5-20m , on the left and right of the post, dig two holes for two braces. the hole size same as the post hole size.
After all the holes finished , Put the posts into the hole. Pay attention to controlling hammer force when the post approaching the depth in construction. Then pouring of concrete like this, the brace install in the same way, and the brace connect with bolts:
次に、コンクリートが十分に乾くまで待つ必要があります。次に、溶接金網フェンス パネルをポストと一緒に取り付けることができます。ポストにフックを作ったので、金網パネルを取り付けるときに、金網パネルをより安定させるために、金網パネルをフックに合わせて配置します。ここでは、フックをハンマーで平らに叩く必要があります。
Firstly, make one end of the tension wire fixed on the first post with the wire tighterner . Secondly, interval of 15meters, the other end of the tension wire fixed on the post , with the wire tighterner, the wire was straightened. and the wire mesh panel was more stable.