Dig the holes on the ground for the post at every 2m, or 2.5m, or 3m, or 5m , the common hole size is 300mm-500mm . depth is 500mm-1000mm. alignment keep them in the line. Every 5-20m , on the left and right of the post, dig two holes for two braces. the hole size same as the post hole size.
After all the holes finished , Put the posts into the hole. Pay attention to controlling hammer force when the post approaching the depth in construction. Then pouring of concrete like this, the brace install in the same way, and the brace connect with bolts:
然後你必須等到混凝土足夠乾燥。然後您可以將電焊網圍欄面板與立柱一起安裝。因為在立柱上,我們做了掛鉤,安裝絲網面板的時候,對齊把線放在掛鉤上,為了讓絲網面板更穩固,這裡需要我們用錘子把掛鉤敲平。
Firstly, make one end of the tension wire fixed on the first post with the wire tighterner . Secondly, interval of 15meters, the other end of the tension wire fixed on the post , with the wire tighterner, the wire was straightened. and the wire mesh panel was more stable.